If you’re renovating a shop lot, fitting out an office, or planning a new commercial unit, you’ll need to make an official application for building plan approval before construction can begin.
Here’s how the building plan submission process typically works for commercial projects in Malaysia:

Step 1: Appoint a Licensed Architect
This is mandatory. Only a registered architect can prepare and submit plans for local authority approval. Your architect will ensure the design meets local council (DBKL, MBPJ, MBSJ, MBSA, MPSepang etc.) guidelines, Uniform Building By-Laws and Fire Regulation.
Step 2: Prepare Supporting Documents
Your architect will coordinate the preparation of required documents, which may include:
- Submission documents such as Land Title, Quit Rent, Assessment, Tenancy Agreement, Sale & Purchase Agreement, etc.
- Submission drawings which include Location and Site Plans, Floor Plans, Sections and Elevations.
- BOMBA Passive Fire Plans.
- Inputs from planner, engineer or other consultants if relevant.
Step 3: Submit via the OSC 3.0 Portal
All plans are submitted digitally via the One Stop Centre (OSC) 3.0 portal. A reference code is generated, allowing for tracking and follow-up with the respective council.
Step 4: Respond to Council Comments
The local authority may request revisions, clarifications, or additional documents. Your architect will handle communications, adjust drawings if needed, and manage the re-submission process.
Step 5: Receive the Approval Letter
Once the plan is approved, you’ll receive formal permission to proceed with the construction or renovation works in accordance with the approved scope.